Modular LivingAustralia

Main page › Guides › Approval process

The approval process for a modular home, step by step

This is the overview. Each step links to a detailed guide, and each state has its own rules page. Terminology differs between states; the table below gives the local names.
Approvals at a glance
Contemporary home with open sliding doors
Illustrative stock image — not a depiction of any specific builder's product.
Same laws as a site-built homeYes — planning, building and plumbing laws apply equally[1]
Planning approvalUsually needed; depends on zone and overlays[2][3]
Building approvalAlways needed for a dwelling[2]
NSW fast-trackComplying development, as little as 20 days[4]
NSW development applicationAverage 70 days to determine[4]
Final stepOccupation or occupancy certificate before moving in[5][6]

A modular home needs the same approvals as a site-built home: the same planning, building and plumbing laws apply to it.[1] In most of Australia that means planning approval, which asks whether the home is allowed on the land, then building approval, which asks whether the design complies with the National Construction Code, and finally a certificate that it can be occupied. In Victoria, for example, a planning permit is usually needed and a building permit is always needed.[2]

What off-site construction changes is when and where the work happens, not whether it is regulated. The steps below follow the order most projects take, with the detailed guide for each.

Step 1 — Check the block §

Get the official planning report for the land before buying or committing to a design. In NSW this is the section 10.7 planning certificate[7]; in Victoria, the Planning Property Report, which also flags bushfire and heritage status.[8] The zone and overlays shown there decide whether a dwelling is allowed and which pathway is open.

Detail: checking a block before you buy for a modular home.

Step 2 — Find the pathway §

Most states have a fast-track pathway for designs that meet standard rules, and a full assessment for everything else. The gap can be large: NSW publishes as little as 20 days for complying development against an average of 70 days for a development application,[4] and South Australia's deemed-to-satisfy pathway has 5 business days against 70 for a notified performance assessment.[9] Overlays such as bushfire, flood and heritage are a common reason a fast-track is not available.

Detail: each state's rules page, listed in the table below.

Step 3 — Lodge, and allow for notification §

Some applications are advertised to neighbours, which adds time and can lead to objections. Since 1 September 2026, many two-storey-or-less homes in NSW that comply with height and floor-space controls are not exhibited at all.[10]

Detail: neighbour notification and objections by state.

Step 4 — The decision §

Each state gives the authority a statutory period to decide. In Western Australia it is 60 days, or 90 if advertised; if it passes, the application can be treated as refused.[3]

Detail: approval timeframes by state.

If the home is refused or the conditions do not work, there are short deadlines to act — 14 days in Tasmania[11], generally 6 months in NSW.[12] Detail: reviews and appeals after a planning decision.

Step 5 — Building approval §

The building approval checks the detailed design against the National Construction Code. Who issues it varies (see the table). In Western Australia a certified building permit application is decided within 10 working days and an uncertified one within 25.[13]

Step 6 — Manufacture, delivery and inspections §

This is where a modular home differs most. Manufacturing can run while the site is prepared, but inspection rules were designed for on-site construction, as the Australian Building Codes Board has acknowledged.[14] Mandatory inspections still happen on site — in Queensland the certifier must personally inspect the final stage of a house.[15] Factory work is checked largely through compliance documents.

Detail: who inspects and certifies a factory-built home and delivery, transport and craneage.

Step 7 — Final certificate §

The home cannot be lived in until the final certificate is issued — an occupation certificate in NSW[5], a Certificate of Occupancy in South Australia.[6]

Keeping the approval alive §

Approvals lapse if work does not start, and design changes after approval may need a formal modification. A Victorian building permit lapses if work has not started within 12 months of issue.[16]

Detail: changing or extending an approval.

Who issues what, by state §

JurisdictionPlanning approvalBuilding approval issued byState guide
NSWDevelopment application, or complying development certificate from council or an accredited certifier[4]Certifier (construction certificate); principal certifier issues the occupation certificate[5]NSW
VictoriaPlanning permit from council, where required[2]Registered private building surveyor appointed by the owner[2]Victoria
QueenslandDevelopment application, where required — lodged, referred, notified if impact assessable, then decided[17]Building certifier[15]Queensland
Western AustraliaDevelopment approval from the local government, depending on zone[3]Local government as permit authority[18]Western Australia
South AustraliaPlanning consent, part of one development approval[19]Council or private building certifier (building consent)[20]South Australia
TasmaniaPlanning permit from the planning authority[21]Building surveyor assesses; permit authority issues the building permit[22][21]Tasmania
ACTDevelopment approval, unless exempt[23]Certifier, after development approval[23]ACT
Northern TerritoryDevelopment permit where the planning scheme requires consent[24]Registered building certifier[25]Northern Territory

Practical points §

  1. Settle the pathway before booking a factory slot. The difference between pathways is measured in weeks or months.[4][9]
  2. Ask the manufacturer which approvals it manages and which remain the owner's responsibility. In Victoria the owner, not the builder, appoints the building surveyor.[2]
  3. Ask which inspections will happen on site after delivery and who books them.
  4. Diary every deadline: decision periods, appeal periods and lapse dates.

What is not covered here §

Application fees and levies (see approval fees and levies by state), developer contributions (see council fees and developer contributions), secondary dwelling rules (see granny flat rules by state), owner-builder permits, transport permits and individual council planning schemes are covered in separate guides or not at all. This guide does not assess whether any particular home will be approved.

Ask Modular Living AI about this guide

Still have a question after reading this guide? Ask it here. The answer draws on this guide, our other guides and the official pages they cite, with links to each one it used.

General information only, not legal, financial or building advice.

The Dispatch — a monthly email when new guides are published. No noise; unsubscribe anytime.

Sent to info@modularlivingaustralia.com.au and handled by a person. See Privacy.

References §

  1. Queensland Building and Construction Commission — Tiny homes FAQs — small prefabricated Class 1a dwellings, including modular units, prefabricated dwellings, transportable buildings, granny flats and secondary dwellings, are subject to the same planning, building and plumbing laws as traditional homes and must meet National Construction Code requirements and obtain all necessary approvals. qbcc.qld.gov.au/home-owner-hub/build-renovate/getting-started/options-building-renovating/faqs-tiny-homes
  2. Victorian Government — Planning and building permits — To build you usually need a planning permit and will always need a building permit; the planning permit is issued by the local council; the building permit is issued by a registered private building surveyor whom the owner, not the builder, must appoint, to keep the surveying process independent. vic.gov.au/planning-and-building-permits
  3. Shire of Dardanup (Western Australia) — WA planning system flowchart — development applications are decided by the local government within 60 days, or 90 days if advertised; deemed refusal if the timeframe is missed; State Administrative Tribunal review within 28 days. dardanup.wa.gov.au/Profiles/dardanup/Assets/ClientData/Documents/Services/WA-Planning-System.pdf
  4. NSW Department of Planning, Housing and Infrastructure — Complying development — fast-tracked complying development approvals can be issued in as little as 20 days; Pattern Book complying developments take 10 days; the average determination time for a development application is 70 days; complying development can be determined by a council or an accredited certifier. Checked 8 October 2026. planning.nsw.gov.au/assess-and-regulate/development-assessment/planning-approval-pathways/complying-development
  5. NSW Government — Approvals needed for your building project — explains the complying development and development application pathways, the construction certificate, the principal certifier and the occupation certificate. nsw.gov.au/housing-and-construction/building-or-renovating-a-home/preparing/approvals
  6. PlanSA (South Australian Government) — Building — development involving building work requires building consent as part of its approval, assessed against the building rules based on the National Construction Code with state variations; a Certificate of Occupancy is required for buildings before occupation, with exceptions. plan.sa.gov.au/resources/building
  7. City of Parramatta — Planning certificates — a section 10.7 certificate gives the information council holds on zoning, planning controls and other property issues; council must issue it on application under the Environmental Planning and Assessment Act 1979. cityofparramatta.nsw.gov.au/development/development-applications/planning-certificates
  8. Victorian Department of Transport and Planning — Planning Property Report — shows the planning zone and overlays for an address, Victorian Heritage Register status, designated bushfire prone area status and areas of Aboriginal cultural heritage sensitivity. planning.vic.gov.au/schemes-and-amendments/planning-report
  9. PlanSA (South Australian Government) — Planning consent assessment timetables — deemed-to-satisfy 5 business days; performance assessed with public notification 70 business days. plan.sa.gov.au/development_applications/getting_approval/how_applications_are_assessed/assessment_stages/assessment_timetables/planning_consent
  10. NSW Department of Planning, Housing and Infrastructure — Statewide Community Participation Plan — took effect on 1 September 2026; a list of lower-impact development types needs no public exhibition where the development is consistent with building height and floor space ratio controls. planning.nsw.gov.au/statewide-community-participation-plan
  11. State Planning Office, Tasmania — What can be appealed — an applicant may appeal a refusal within 14 days. stateplanning.tas.gov.au/planning-system/appeals-and-enforcement/what-can-be-appealed
  12. Land and Environment Court of NSW — Development application appeals — an applicant may appeal generally within 6 months after notice of the determination or the date it is taken to have been determined. lec.nsw.gov.au/types-of-cases/class-1---environmental-planning-and-protection-appeals/development-application-appeals.html
  13. Shire of Peppermint Grove (Western Australia) — Building permits — a certified application is to be issued within 10 working days and an uncertified application within 25 working days. peppermintgrove.wa.gov.au/development/building/building-permits.aspx
  14. Australian Building Codes Board — Consultation news item (2025) — conventional building certification processes and inspection regimes were developed for construction built on site and present challenges for buildings manufactured off site and transported for installation. abcb.gov.au/news/2025/consultation-open-national-voluntary-certification-scheme-manufacturers-modern-methods-construction
  15. Business Queensland — For single detached Class 1a buildings, the building certifier must personally inspect the final stage; for aspects of the excavation, footings and slab stages a certifier can rely on a suitably qualified competent person. business.qld.gov.au/industries/building-property-development/building-construction/approvals-inspections/competent-persons-cadets
  16. Victorian Building Authority (trading as Building and Plumbing Commission) — Practice Note BP-07 — Building work must commence within 12 months of the building permit being issued and a Class 1 building must be completed within 24 months, otherwise the permit lapses. bpc.vic.gov.au/__data/assets/pdf_file/0019/21484/BP-07-Time-Limits-for-building-work-and-lapse.pdf
  17. Queensland Government — Development assessment process — the formal process has five parts — lodging, referral, information request, public notification and decision — not all of which apply to every application; applicants can change an existing approval or extend its timeframe before it lapses. planning.statedevelopment.qld.gov.au/planning-framework/development-assessment/development-assessment-process
  18. Government of Western Australia — Building and Energy — A building permit application is assessed by the relevant local government, which acts as the permit authority under the Building Act 2011. wa.gov.au/organisation/building-and-energy/building-approvals
  19. PlanSA (South Australian Government) — Types of consent — development approval consists of one or more consents granted during assessment, such as planning consent and building consent, depending on what is proposed and where, under the Planning, Development and Infrastructure Act 2016. plan.sa.gov.au/development_applications/getting_approval/how_applications_are_assessed/types_of_consent
  20. Law Handbook SA (Legal Services Commission of South Australia) — Building consent for accepted development is assessed by local councils or a private building certifier. lawhandbook.sa.gov.au/ch28s02s03s03.php
  21. PlanBuild Tasmania — A planning permit is a statutory licence issued by a planning authority to carry out approved development; a building permit is a statutory licence issued by a permit authority to carry out approved building work. planbuild.tas.gov.au/enquiry-service/using-planbuild
  22. State Planning Office, Tasmania — Licensed building surveyors assess proposed design and building work against the building legislation. stateplanning.tas.gov.au/topics/building
  23. ACT Planning — Building approvals — development approval is needed before building approval; a certifier must be appointed and forms lodged with Access Canberra. planning.act.gov.au/applications-and-assessments/building-approvals
  24. Northern Territory Government — Getting a building permit — building permits are required in building control areas; a development permit is required where the NT Planning Scheme requires consent and must be obtained before applying for a building permit. nt.gov.au/property/building/build-or-renovate-your-home/building-and-renovating-permits-and-processes/getting-a-building-permit
  25. Northern Territory Government — Building certification process — the building certifier assesses the application for compliance with the Building Act, the Building Regulations and the National Construction Code; building permits are valid for two years from issue. nt.gov.au/property/building/build-or-renovate-your-home/building-and-renovating-permits-and-processes/building-certification-process

Figures are as published by the sources above at their respective dates and are paraphrased summaries, not verbatim reproductions. Verify current pricing and rules directly with builders, lenders and planning authorities.