This page describes how the National Construction Code and state approval processes apply in general. Each building is assessed by its own certifier or building surveyor; nothing here is an approval decision or compliance advice.
3D-printed homes at a glance
Separate rulebook?No dedicated 3D-printing pathway is named in the ABCB handbook; the general NCC compliance pathways apply[1]
PathwaysDeemed-to-Satisfy Solution, Performance Solution, or a combination[1]
Product evidenceIncludes test reports, certificates and CodeMark certificates of conformity[1][2]
First NSW social housing exampleTwo two-bedroom homes in Dubbo; council approved the development application in July 2024[3][4]

A 3D-printed home is built by a machine depositing material, usually a cementitious mix, in layers to form walls or other parts. In Australia it is not a separate legal category of building. As far as the official sources compiled here show, it is assessed against the same National Construction Code (NCC) as any other building, using the same compliance pathways.[1] What is different is the evidence a certifier may need to be satisfied that a new method performs as the code requires.

How the NCC treats additive manufacturing §

The Australian Building Codes Board (ABCB) handbook on prefabricated, modular and offsite construction has a section on additive manufacturing, grouped with subtractive methods such as CNC cutting. It describes printing in plastics, resins or cementitious mixes, producing either non-structural parts or load-bearing elements, and likens load-bearing concrete printing to in-situ concrete walls built without formwork.[1] The ABCB's own initiative page lists 3D printing among the modern methods of construction the handbook is meant to help practitioners apply.[2]

The handbook does not set out a printing-specific compliance route. Its general framework applies instead.[1]

PathwayEvidence it can useVerification Methods?
Deemed-to-Satisfy (DTS) SolutionEvidence of suitability; expert judgementNot available
Performance SolutionTests, inspections, calculations; expert judgement; comparison with DTSAvailable
CombinationParts of each, as relevantFor the Performance parts

In practice, a printed wall that does not match the way the DTS provisions describe a material or construction form would be a matter for the Performance Solution route, because that route lets the documentation set out the evidence and verification needed, including for parts that end up concealed.[1] The handbook says this about Performance Solutions generally; it does not say which route any particular printed system has used.

Evidence of suitability and CodeMark §

The handbook lists the kinds of evidence of suitability that can support a product or system: certificates, test reports from an accredited testing laboratory, and CodeMark certificates.[1] CodeMark is a voluntary, third-party certification scheme run by the ABCB for new or innovative building products, and a CodeMark certificate of conformity is one accepted way under the NCC to show suitability.[5] Whether a building control authority must accept a certificate depends on state and territory law, policy or directives.[5] For related testing and certification bodies, see building product testing and certification bodies, and for the Australian Standards that sit beneath the code, see Australian Standards for prefab buildings.

The handbook also flags practical points specific to printing: offsite printed components need careful handling, transport and storage; interfaces with in-situ construction (connections, dimensional tolerances, dissimilar materials) must be designed; and design coordination and site supervision are described as crucial.[1]

A worked example: Dubbo, NSW §

The clearest public example in the sources compiled here is a pair of two-bedroom homes on a vacant block in Dubbo for Aboriginal Housing Office (AHO) tenants. They were delivered by Aboriginal Sustainable Homes with the 3D-construction company Contour3D.[3][4] Dubbo Regional Council approved the development application under delegated authority on 31 July 2024.[3]

The NSW Government describes this as the state's first 3D-printed social housing and as a test of whether the method can deliver social and affordable homes faster and more sustainably.[4] The government announced completion in May 2025.[6]

The figures below are the NSW Government's and the AHO's own statements about their project, not independent measurements.

ItemStated figureSource
Printing timeAbout 16 daysNSW Government[4][6]
Total build time20 weeks, against a usual 40NSW Government[6]
Concrete usedAbout 70 tonnesNSW Government[4]

The earlier AHO page and the November 2024 release projected a 16-week build; the May 2025 announcement reports 20 weeks.[3][4][6] None of these pages states which NCC pathway or evidence of suitability the project relied on, and the completion announcement names no standards, certifications or cost figures.[6] The Dubbo project shows that a council can approve a development application for a printed building. It does not show how the building's technical compliance was documented.

How this relates to other prefab methods §

Printing sits within the wider group of modern methods of construction that the ABCB handbook addresses, alongside volumetric modules and panelised systems.[1][2] NSW's supplier procurement list for government housing also lists additive manufacturing among the product categories it covers; see selling prefab to government. For the general approval sequence for factory-built homes, see the modular home approval process and factory-built home inspections and certification.

What is not covered here §

This page does not identify which 3D-printed systems hold a CodeMark certificate, an accredited test report or a Performance Solution report. The sources compiled here do not list any.

It does not cover state-by-state differences in how certifiers accept evidence for printed construction, planning approval for printed homes outside the Dubbo example, or approvals for other Australian printed projects (in Victoria, Western Australia or elsewhere), because no official approval records for those were compiled here. Media coverage of other projects exists but is not used as a source on this page.

There are no independent figures here for cost, durability, thermal performance, insurance or warranty treatment, or finance availability for printed homes. The handbook was read as published for NCC 2022; whether NCC 2025 changed any relevant wording is not covered by sources compiled here. See what changes under NCC 2025 for the edition change in general.

Ask Modular Living AI about this guide

Still have a question after reading this guide? Ask it here. The answer draws on this guide, our other guides and the official pages they cite, with links to each one it used.

General information only, not legal, financial or building advice.

The Dispatch — a monthly email when new guides are published. No noise; unsubscribe anytime.

Sent to info@modularlivingaustralia.com.au and handled by a person. See Privacy.

References §

  1. Australian Building Codes Board — Prefabricated, modular and offsite construction handbook (NCC 2022), version 1.1, December 2024 — Section 3.10 covers additive manufacturing (3D printing) alongside subtractive methods. Describes layer-by-layer printing in plastics, resins or cementitious mixes, for non-structural or load-bearing elements, and load-bearing concrete printing as comparable to in-situ concrete walls built without formwork. Notes handling, transport and storage of offsite printed parts, design of interfaces with in-situ work (connections, tolerances, dissimilar materials), and the importance of design coordination and site supervision. Does not set out a 3D-printing-specific pathway; the general framework applies: a Deemed-to-Satisfy (DTS) Solution, a Performance Solution, or a combination. DTS allows evidence of suitability and expert judgement but not Verification Methods; a Performance Solution can use Verification Methods, expert judgement or comparison with DTS Provisions. Evidence of suitability can include certificates, test reports from an accredited testing laboratory and CodeMark certificates. The first 100,000 characters of the document were read. nccb.gov.au/sites/default/files/resources/2024/Prefabricated%2C%20modular%20and%20offsite%20construction%20handbook%20NCC%202022%20Final.pdf
  2. Australian Building Codes Board — Prefabricated, modular and offsite construction (initiative page) — Handbook published November 2024, one of three resources to help practitioners apply modern methods of construction, prepared at the request of Building Ministers. Describes modern methods of construction as including 3D printing, robotics and artificial intelligence. Lists companion resources 'Evidence of suitability' and 'Performance Solution Process' (both September 2024). The page does not explain how 3D printing specifically is assessed. nccb.gov.au/initiatives/prefabricated-modular-and-offsite-construction
  3. Aboriginal Housing Office (NSW) — AHO's 3D printed homes get the green light in Dubbo — Dubbo Regional Council approved the development application under delegated authority on 31 July 2024. Two two-bedroom duplexes with 3D-printed walls on a vacant block; delivered by Aboriginal Sustainable Homes with Contour3D; part of the AHO Closing the Gap Housing Solutions Program. The page states the AHO expects about 60 per cent less build time (40 weeks to 16). The only regulatory item on the page is the council approval. The page's original publication date is not stated. aho.nsw.gov.au/about-us/news/ahos-3d-printed-homes-get-green-light-dubbo.html
  4. NSW Government — Construction begins on NSW's first 3D-printed social housing project (media release, 11 November 2024) — Issued by the NSW Minister for Homelessness and Minister for Housing. Construction started in Dubbo on what the government calls the state's first 3D-printed social housing: two two-bedroom duplexes for Aboriginal Housing Office tenants, developed by Aboriginal Sustainable Homes with Contour3D. States Dubbo Regional Council approved the development application in July 2024. Printed structures expected to take about 16 days using about 70 tonnes of Contour3D's proprietary printable concrete. Describes the project as a test of whether the method can deliver social and affordable homes faster across the state. Mentions no other approvals or standards. nsw.gov.au/media-releases/construction-begins-on-nsws-first-3d-printed-social-housing-project
  5. ABCB — CodeMark: what is CodeMark — CodeMark is a voluntary third-party certification scheme run by the Australian Building Codes Board to help show that new or innovative building products meet the NCC. Under the NCC a CodeMark certificate of conformity is one accepted way to show a product is suitable for use. Whether building control authorities must accept a certificate depends on state and territory legislation, policy or directives, and the page advises checking with the local authority. codemark.abcb.gov.au/building-practitioners/what-codemark
  6. NSW Government — NSW's first ever 3D-printed social homes now complete (Homes NSW news, 15 May 2025) — Government announcement that the two Dubbo homes were complete, with move-in expected in May 2025. Says the project took 20 weeks against a usual 40-week timeline and the concrete structures were printed in 16 days. Names no standards, certifications or approvals, and gives no cost figures. The descriptions of the homes are the government's own. nsw.gov.au/departments-and-agencies/homes-nsw/news/nsws-first-ever-3d-printed-social-homes-now-complete

Figures are as published by the sources above at their respective dates and are paraphrased summaries, not verbatim reproductions. Verify current pricing and rules directly with builders, lenders and planning authorities.